BOND ISSUE
- Bond Issue Board Update - February 10, 2021
- Bond Issue Board Update - January 13, 2021
- Bond Issue Board Update - December 9, 2020
- Bond Issue Board Update - November 11, 2020
- Bond Issue Board Update - October 14, 2020
- Bond Issue Board Update - September 23, 2020
- Bond Issue Board Update - August 26, 2020
- Bond Issue Progress - Phase 1 & 1.5
- Bond Issue Progress - Phase 2
Bond Issue Board Update - February 10, 2021
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
JH&H PROJECTS
◼︎New Northwest Rankin High School
- Contractor continues to install metal panels, aluminum canopies, curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). Millwork and markerboards installation continues. All trades are in progress.
- Courtyard work is underway.
- Site work continuing to progress.
- Project is currently scheduled for completion mid-March.
◼︎Pisgah Elementary
-
Renovation work to the existing school is nearing completion.
- PE/Classroom addition and Connecting Corridor is dried in. Interior work is underway. All trades are in progress.
- Site work (utilities, storm drainage, parking lot replacement, emergency access lane) continues to progress.
◼︎Flowood Elementary School Additions and Renovations
- Renovation work to the existing school is complete.
- PE/Classroom addition and Connecting Corridor is dried in. Interior work is underway. All trades are in progress.
- Site work (rough grading, storm drainage, utilities, and grading) substantially complete. Fine grading and seed/sod to be completed as project nears completion.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
- Project is nearing substantial completion.
- Contractor is working to correct preliminary punch list items.
◼︎EXISTING NORTHWEST RANKIN HIGH SCHOOL RENOVATIONS – PHASE 3
-
Project is on the market for bidding. Received bids 2/18.
◼︎EXISTING NORTHWEST RANKIN MIDDLE SCHOOL RENOVATIONS
- Project is on the market for bidding.
- Project to be included with Existing Northwest Rankin High School Renovations – Phase 3.
DALE/BAILEY PROJECTS
◼︎Brandon Middle School
-
Building Package
-
Plumbers making connections on rooftop equipment for startup
- Masonry work is on going
- New construction interior finishes are ongoing
- Interior renovation punch list is being completed by the contractor
◼︎McLaurin High School
-
Cafeteria addition:
-
Punch list created
-
-
Classroom addition:
-
Cleaning masonry
- Beginning interior work
-
- Existing Gym:
- Brick installation complete
- Work on exterior punchlist
- Existing Toilets:
- Ready for inspection
◼︎Pelahatchie High School
-
Contractor preparing closeout documents
- Contractor is working off punchlist items
◼︎Puckett High School
-
Polished concrete floors are still on-going and inspection
- Interior final trim out is nearing completion
- Some exterior paving needs to be completed when weather allows
◼︎Brandon High School
-
The addition has been occupied
- Contractor is working off any punch list items nights/weekends
◼︎Stonebridge Elementary
-
Contractor is completing final punchlist items
- Contractor is preparing closeout documents
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
-
GC is working off punchlist items
- Completing walkway canopy awaiting installation.
◼︎Florence High School
-
Interior demo is complete
- Installing masonry
- Continuing new addition CMU
- MEP contractors continuing with rough in
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
Building 100 (New Classroom Building)
-
Building is in the dry
- Completing second floor masonry
- MEP rough ins are nearing completion
Building 3000 (Cafeteria)
-
Ready for inspection
Building 4000 (Fine Arts Building)
-
Contractor is continuing interior finishes
Building 7100 (Ag Shop)
-
Roof and wall panels are nearing completion
-
MEP contractors working on rough ins where dry
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
Pelahatchie Elementary |
Northshore Elementary |
Pisgah High School |
Oakdale Elementary |
NWR HS Site Package |
Highland Bluff Elementary |
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
Existing NWR HS Renovations Phase I |
Brandon Elementary |
Steen’s Creek Elementary |
Puckett High Dressing Room |
Florence Elementary |
Puckett Elementary School |
NWR Middle Reroof |
Florence Middle Reroof |
NWR Elementary Reroof |
Special Needs Playgrounds |
NWR Elementary Additions & Renovations |
Richland Elementary School |
Bond Issue Board Update - January 13, 2021
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
JH&H PROJECTS
◼︎New Northwest Rankin High School
-
Contractor continues to install metal panels, aluminum canopies, curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). Millwork and markerboards installation continues. All trades are in progress.
- Courtyard work is underway.
- Site work continuing to progress.
- Project is on schedule.
◼︎Pisgah Elementary
-
Renovation work to the existing school is nearing completion.
- Coordination of construction activities and school staff continues.
- PE/Classroom addition and Connecting Corridor is dried in. Interior work is underway. All trades are in progress.
- Cafeteria expansion is complete.
- Contractor has encountered some unknown underground utilities and has impeded some progress and those issues are being addressed.
- Site work (utilities, storm drainage, parking lot replacement, emergency access lane) continues to progress.
◼︎Flowood Elementary School Additions and Renovations
-
Renovation work to the existing school is complete.
- Coordination of construction activities and school staff continues.
- Work on PE/Classroom addition and Connection Corridor continues. Storefront installed. Interior work is underway. All trades are in progress.
- Site work (storm drainage, utilities, and grading) continues.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
-
Project is nearing substantial completion.
- Contractor is working to correct preliminary punch list items.
◼︎EXISTING NORTHWEST RANKIN HIGH SCHOOL RENOVATIONS – PHASE 3
-
Project planning/scope development underway
◼︎EXISTING NORTHWEST RANKIN MIDDLE SCHOOL RENOVATIONS
-
Project is scheduled to be put on the market this month.
- Project to be included with Existing Northwest Rankin High School Renovations – Phase 3.
DALE/BAILEY PROJECTS
◼︎Brandon Middle School
-
Building Package
-
Plumbers running gas lines on roof
- Brick work ongoing
- New construction interior finishes beginning
- Interior renovation punch list is being reviewed
◼︎McLaurin High School
-
Cafeteria addition: ▪ Ready for punch list
-
Classroom addition: ▪ Laying brick
-
Completing Brick and Roofing
-
Existing Gym: ▪ Brick installation complete
-
Window scope ready for inspection
-
Replacing downspouts
-
Existing Toilets: ▪ Last set to complete this month
◼︎Pelahatchie High School
-
Contractor preparing closeout documents
- Restroom renovations ready for punchlist
◼︎Puckett High School
-
Contractor is preparing to polish concrete floors – remains ongoing, not accepted by architect
- Contractor is installing ceramic tile in toilets
- Contractor awaiting revised asphalt layout
- Installing doors and hardware
◼︎Brandon High School
-
Contractor working off punch list items
- Reviewing required work for asphalt paving
◼︎Stonebridge Elementary
-
Substantial Completion Inspection was held November 30, 2020
- Contractor is completing punchlist items
- Contractor is preparing closeout documents
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
-
Owner and Architect punch lists have been distributed to GC.
- GC is currently performing punch list work.
- New bus canopy is complete. Adjacent walkway canopy awaiting installation.
◼︎Florence High School
-
Interior Selective repairs are approx. 90% complete. Carpet was installed in the Library over the Thanksgiving break. Remaining VCT repairs will occur during a school break.
- Foundation work, CMU masonry, and roof framing for the new Administration office and connection corridor is complete; exterior masonry for the addition is on site and work will resume in this area.
- North parking lot is complete.
- First floor slab for the new building is complete.
- CMU masonry for the new classroom building is underway. Exterior CMU installation is approximately 25% complete.
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
Building 100 (New Classroom Building)
-
Roof insulation and base sheet have been installed.
-
Second floor masonry walls are nearing completion.
- Electrical rough-ins installation continues on the second floor.
- Duct work installation on first and second floor is ongoing.
- Fire Sprinkler system installation in progress on second floor.
- Plumbing rough-ins installation ongoing.
- Brick masonry wall is in progress.
Building 3000 (Cafeteria)
-
Work is nearing completion.
-
Inspection to be schedule by mid-January pending Contractor’s request.
Building 4000 (Fine Arts Building)
-
Interior wall prep and painting on going
-
Floor tile installation had commenced.
-
Mechanical and electrical rough ins continue.
-
Exterior brick wall is completed.
Building 7100 (Ag Shop)
-
Metal roof and wall panels have been installed.
-
Mechanical and electrical rough ins are in progress.
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
Pelahatchie Elementary |
Northshore Elementary |
Pisgah High School |
Oakdale Elementary |
NWR HS Site Package |
Highland Bluff Elementary |
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
Existing NWR HS Renovations Phase I |
Brandon Elementary |
Steen’s Creek Elementary |
Puckett High Dressing Room |
Florence Elementary |
Puckett Elementary School |
NWR Middle Reroof |
Florence Middle Reroof |
NWR Elementary Reroof |
Special Needs Playgrounds |
NWR Elementary Additions & Renovations |
Richland Elementary School |
Bond Issue Board Update - December 9, 2020
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
JH&H PROJECTS
◼︎New Northwest Rankin High School
-
Contractor continues to install metal panels, aluminum canopies, curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). All trades are in progress.
- Courtyard work is underway.
- Site work continuing to progress.
- Project is on schedule.
◼︎Pisgah Elementary
-
Renovation work to the existing school is nearing completion.
- Coordination of construction activities and school staff continues.
- PE/Classroom addition and Connecting Corridor CMU walls are complete and roofing in place. Interior work is underway.
- Cafeteria expansion is complete.
- Contractor has encountered some unknown underground utilities and those issues are being addressed.
- Site work (utilities, storm drainage, parking lot replacement, emergency access lane) continues to progress.
◼︎Flowood Elementary School Additions and Renovations
-
Renovation work to the existing school is nearing completion.
- Coordination of construction activities and school staff continues.
- PE/Classroom addition and Connection Corridor CMU is complete. Roof is dried in.
- Brickwork is scheduled to begin this month.
- Asphalt paving and striping is complete. Site work (storm drainage, utilities, and grading) continues.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
-
Interior finish nears completion at the high school building and annex.
- HVAC unit replacements are nearing completion.
- Connection between main building and vine street (canopies and fencing) is in progress.
◼︎EXISTING NORTHWEST RANKIN HIGH SCHOOL RENOVATIONS – PHASE 3
-
Project planning/scope development underway
◼︎EXISTING NORTHWEST RANKIN MIDDLE SCHOOL RENOVATIONS
-
Project planning/scope development underway
DALE/BAILEY PROJECTS
◼︎Brandon Middle School
-
Building Package
- Plumbers running gas lines on roof
- Brick work ongoing
- Laying ceiling grid and furred downs
- Hanging sheetrock
- Contractor to complete punchlist on windows and painting during the holidays
- Next OAC scheduled for 12/16/20 at 9:45 AM.
◼︎McLaurin High School
-
Cafeteria addition: • Preparing to wax VCT
- Classroom addition: • Laying brick
- Installing roofing systems
- Existing Gym: ▪ Brick installation complete
- Window scope of work to be done over Christmas break
- Replacing downspouts
- Existing Toilets: ▪ 14 of the 19 toilets are complete
- Next OAC scheduled for 01/06/21 at 9:30 AM.
◼︎Pelahatchie High School
-
Contractor preparing closeout documents
- Contractor preparing to finish toilet renovations during the Christmas holidays
- Next OAC scheduled for 12/09/20 at 1:00 PM.
◼︎Puckett High School
-
Contractor is preparing to polish concrete floors
- Contractor is installing ceramic tile in toilets
- Contractor awaiting revised asphalt layout
- Canopy has been installed
- Painting ongoing
- Next OAC scheduled for 01/06/21 at 8:00 AM.
◼︎Brandon High School
-
Asphalt resurfacing is complete
- Contractor is working off Contractor’s Punchlist
- Installing aluminum doors at loggia
- Fire alarms devices are installed
- Installing rubber flooring in PE and stairs treads
- Painting is ongoing
- Architect awaiting pricing for West Gate
- Substantial Completion has been scheduled for Wednesday, December 16, 2020 @ 11:30AM
◼︎Stonebridge Elementary
-
Substantial Completion Inspection was held November 30, 2020
- Contractor is completing punchlist items
- Contractor is preparing closeout documents
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
-
Work is complete in existing building.
- New connector breezeway is complete.
- Building sign is to be installed this week.
- New bus canopy is complete. Adjacent walkway canopy awaiting installation.
- Work at GED building is complete.
◼︎Florence High School
-
Interior Selective repairs are approx. 90% complete. Carpet was installed in the Library over the Thanksgiving break. Remaining VCT repairs will occur during the Christmas holidays.
- Foundation work, CMU masonry, and roof framing for the new Administration office and connection corridor is complete.
- Exterior work on the new Administration office will recommence once masonry and roofing materials arrive on site.
- North parking lot is complete.
- First floor slab for the new building is 90% complete. Final pour will occur the week of 11/30, weather permitting.
- Concrete masonry for the new classroom building to begin as soon as weather permits.
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
Building 100 (New Classroom Building)
- Roof structure and deck have been installed.
- Second floor masonry walls are nearing completion.
-
Electrical rough-ins installation continues on the first floor.
- Duct work installation on first floor is ongoing.
- Fire Sprinkler system installation in progress on first floor.
- Electrical and plumbing rough-ins installation ongoing on the second floor.
- First coat of damp-proofing on exterior masonry wall is in progress.
- Exterior wood blocking at roof and exterior openings has commenced.
Building 3000 (Cafeteria)
- Shingle color is not accepted; new shingles will be installed over spring break
- We will coordinate with the contactor for a solution.
- Site grading nearing completion
- Paint and flooring installation is nearing completion.
Building 4000 (Fine Arts Building)
- Interior wall prep and painting on going
- Additional furr outs have been added.
- Mechanical and electrical rough ins continue.
- Exterior brick wall is nearing completion
Building 7100 (Ag Shop)
- Pre-Engineer Metal Building primary structural frame has been erected.
- Secondary framing is on progress.
- Items requiring correction in occupied buildings will be corrected during the Christmas break.
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
Pelahatchie Elementary |
Northshore Elementary |
Pisgah High School |
Oakdale Elementary |
NWR HS Site Package |
Highland Bluff Elementary |
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
Existing NWR HS Renovations Phase I |
Brandon Elementary |
Steen’s Creek Elementary |
Puckett High Dressing Room |
Florence Elementary |
Puckett Elementary School |
NWR Middle Reroof |
Florence Middle Reroof |
NWR Elementary Reroof |
Special Needs Playgrounds |
NWR Elementary Additions & Renovations |
Richland Elementary School |
Bond Issue Board Update - November 11, 2020
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
DALE/BAILEY PROJECTS
◼︎New Northwest Rankin High School
-
Contractor continues to methodically lay CMU, AMU & brick, install curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). All trades are in progress.
-
Site work continuing to progress.
-
Project is on schedule.
◼︎Pisgah Elementary
- Renovation work to the existing school is nearing completion.
- Coordination of construction activities and school staff continues.
- PE/Classroom addition and Connecting Corridor CMU walls are complete. Roof Framing is in progress.
- Cafeteria expansion are nearing completion.
- Contractor has encountered some unknown underground utilities and has impeded some progress. – These issues are being addressed
- Site work (utilities, storm drainage, parking lot replacement, emergency access lane) continues to progress.
◼︎Flowood Elementary School Additions and Renovations
- Renovation work to the existing school is nearing completion.
- Coordination of construction activities and school staff continues.
- PE/Classroom addition and Connection Corridor CMU is complete. Roof is dried in.
- Asphalt paving and striping is complete. Site work (storm drainage, utilities, and grading) continues.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
- Interior finish nears completion at the high school building and annex.
- Coordination of construction activities and school staff occurring.
- Connection between main building and vine street (sidewalks and fencing) is in progress.
◼︎EXISTING NORTHWEST RANKIN HIGH SCHOOL RENOVATIONS – PHASE 3
- Project planning/scope development underway
◼︎EXISTING NORTHWEST RANKIN MIDDLE SCHOOL RENOVATIONS
- Project planning/scope development underway
DALE/BAILEY PROJECTS
◼︎Brandon Middle School
- Building Package
- Plumbers are rough in in the kitchen
- Wires are being pulled in cafeteria/kitchen
- Duct is being installed in cafeteria/kitchen
- Roof is approximately 90% complete
- Contractor to complete punchlist on windows and painting during the holidays
◼︎McLaurin High School
- Ready for Owner’s inspection punchlist
- Cafeteria addition:
- Preparing to wax VCT
- Awaiting blinds to arrive on site to install
- Classroom addition:
- Laying of CMU is complete
- Steel erection beginning
◼︎Pelahatchie High School
- Contractor is preparing close out documents
- Contractor working on partial substantial punchlist
◼︎Puckett High School
- Stage lighting installed
- Contractor awaiting revised asphalt layout
- Canopy is being installed
- Painting ongoing
◼︎Brandon High School
- Polishing concrete floors
- Finish grading is ongoing
- Installing LAT
- Architect awaiting pricing for West Gate
◼︎Stonebridge Elementary
- Interior painting is ongoing
- Fine grading of the site is on going
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
- Work is complete in existing building.
- New connector breezeway is 95% complete.
- Remaining windows in new addition have been installed.
- New bus canopy is complete. Adjacent walkway canopy awaiting installation.
- Work at GED building is complete.
◼︎Florence High School
- Interior Selective repairs are approx. 90% complete. Carpet to be installed in the library and VCT in select classrooms when the school is on Thanksgiving break.
- Foundation work, CMU masonry, and roof framing for the new Administration office and connection corridor is complete.
- Further work in the new Admin office area is on hold pending exterior color selections approval.
- North parking lot is complete.
- Grade beams are complete. First floor slab to be poured in two parts, starting week of 11/9.
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
Building 100 (New Classroom Building)
- Second floor slab has been competed
- Second floor masonry load bearing walls are in progress.
- Electrical and plumbing rough-ins installation ongoing on the first floor.
- Duct work installation on first floor is in progress.
Building 3000 (Cafeteria)
- Shingle color will be review as variation in the shingles colors are noticeable.
- Sidewalk, grading nearing completion
- Interior wall prep and painting ongoing.
- Ceiling installation in progress
Building 4000 (Fine Arts Building)
- Window restoration nearing completion
- Interior wall prep and painting on going
- Mechanical and electrical rough ins continue.
- Accent brick has been order.
- Exterior brick walls work will resume as soon as bricks are on site.
Building 7100 (Ag Shop)
- Manufacturing of building had been released and scheduled for delivery on 11/10/11.
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
Pelahatchie Elementary |
Northshore Elementary |
Pisgah High School |
Oakdale Elementary |
NWR HS Site Package |
Highland Bluff Elementary |
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
Existing NWR HS Renovations Phase I |
Brandon Elementary |
Steen’s Creek Elementary |
Puckett High Dressing Room |
Florence Elementary |
Puckett Elementary School |
NWR Middle Reroof |
Florence Middle Reroof |
NWR Elementary Reroof |
Special Needs Playgrounds |
NWR Elementary Additions & Renovations |
Richland Elementary School |
Bond Issue Board Update - October 14, 2020
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
DALE/BAILEY PROJECTS
◼︎New Northwest Rankin High School
- Contractor continues to methodically lay CMU, AMU & brick, install curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). All trades are in progress.
- Site work continuing to progress. Connection canopy & sidewalks to existing middle school is complete.
- Project is on schedule.
◼︎Pisgah Elementary
- Renovation work to the existing school is in progress.
- Coordination of construction activities and school staff continues.
- PE and Classroom building addition foundation complete. CMU walls in progress.
- Cafeteria expansion in progress. Interior portions of the dining and serving areas are mostly complete.
- Site work (utilities, storm drainage, parking lot replacement, emergency access lane) is in progress.
◼︎Flowood Elementary School Additions and Renovations
- Renovation work to the existing school is in nearing completion.
- Coordination of construction activities and school staff continues.
- PE and classroom building addition foundation work and laying exterior CMU is complete. Roof is in progress. Plumbing & electrical rough-ins in progress.
- Connection corridor foundation work and laying CMU is mostly complete. Roof is in progress. Plumbing & electrical rough-ins in progress.
- Asphalt paving and striping is complete. Site work (storm drainage, utilities, and grading) continues.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
- Interior finish work continues at main high school building and annex.
- Coordination of construction activities and school staff occurring.
- Connection between main building and vine street (sidewalks and fencing) is in progress.
◼︎EXISTING NORTHWEST RANKIN HIGH SCHOOL RENOVATIONS – PHASE 3
- Project planning/scope development underway
◼︎EXISTING NORTHWEST RANKIN MIDDLE SCHOOL RENOVATIONS
- Project planning/scope development underway
◼︎Brandon Middle School
- Building Package
- District has approved color of brick
- Contractor awaiting approval of carpet & VCT
- Installation of HVAC is ongoing
- Architect awaiting for Contractor’s partial substantial punchlist on windows and painting
◼︎McLaurin High School
- Ready for Owner’s inspection punchlist
- Cafeteria addition: ▪ Preparing to wax VCT
- Awaiting blinds to arrive on site to install
- Classroom addition: ▪ Laying of CMU is complete
- Preparing to erect steel
◼︎Pelahatchie High School
- Installing concrete in courtyard
- Contractor working on partial substantial punchlist
◼︎Puckett High School
- Completed block/brick in courtyard except for stone cap
- Installing ceiling grid
- State hardware is completed
- HVAC installation ongoing
◼︎Brandon High School
- Polishing concrete floors
- Finish grading is ongoing
- Installing LAT
- Architect awaiting pricing for West Gate
◼︎Stonebridge Elementary
- Contractor will be cleaning brick on 10/9 and 10/10
- Exterior doors will be relocated week of 10/12th
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
- Work is complete in existing building, minus new carpet in library.
- New connector breezeway is complete.
- Interior finishes of the band and choir rooms ongoing
◼︎Florence High School
- Interior Selective repairs are approx. 90% complete. Carpet in the library and VCT in select classrooms when the school is on a holiday break.
- New front entry exterior is ready for masonry
- Classroom addition foundation is continuing
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
Building 100 (New Classroom Building)
- Contractor has removed all of the concrete deck off the metal deck.
- Deck over the fire academy was damaged and it was required to be removed.
- Installation of new deck over the fire academy to be this week
- New concrete placement schedule for next week.
Building 3000 (Cafeteria)
- Reroofing completed.
- Interior work to start next week.
Building 4000 (Fine Arts Building)
- Mechanical and electrical rough ins continue.
- Exterior brick walls are in progress.
- Approval of accent brick is pending.
- Steel window restoration in progress
Building 7100 (Ag Shop)
- Manufacturing of building had been released.
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
Pelahatchie Elementary |
Northshore Elementary |
Pisgah High School |
Oakdale Elementary |
NWR HS Site Package |
Highland Bluff Elementary |
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
Existing NWR HS Renovations Phase I |
Brandon Elementary |
Steen’s Creek Elementary |
Puckett High Dressing Room |
Florence Elementary |
Puckett Elementary School |
NWR Middle Reroof |
Florence Middle Reroof |
NWR Elementary Reroof |
Special Needs Playgrounds |
NWR Elementary Additions & Renovations |
Richland Elementary School |
Bond Issue Board Update - September 23, 2020
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
JH&H PROJECTS
◼︎New Northwest Rankin High School
- Contractor continues to methodically lay CMU, AMU & brick, install curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). All trades are in progress.
- Site work continuing to progress. Connection canopy & sidewalks to existing middle school is complete.
- Project is on schedule.
◼︎Pisgah Elementary
- Renovation work to the existing school is in progress (interior finishes and lighting).
- Coordination of construction activities and school staff continues.
- PE and Classroom building addition foundation complete. CMU walls in progress.
- Cafeteria expansion in progress. Interior portions of the dining and serving areas are mostly complete.
- Site work (storm drainage, parking lot replacement) is in progress.
◼︎Flowood Elementary School Additions and Renovations
- Renovation work to the existing school is in nearing completion.
- Coordination of construction activities and school staff continues.
- PE and classroom building addition foundation work CMU complete. Roof structure in progress.
- Connection corridor foundation work is complete. CMU walls in progress.
- Asphalt paving and striping is complete. Site work continues.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
- Interior finish work continues at main high school building and annex.
- Coordination of construction activities and school staff occurring.
- Connection between main building and vine street (sidewalks and fencing) is in progress.
◼︎EXISTING NORTHWEST RANKIN HIGH SCHOOL RENOVATIONS – PHASE 3
- Project planning/scope development underway
◼︎EXISTING NORTHWEST RANKIN MIDDLE SCHOOL RENOVATIONS
- Project planning/scope development underway
DALE/BAILEY PROJECTS
◼︎Brandon Middle School
Building Package
- Contractor awaiting approval of brick
- Contractor awaiting approval of carpet & VCT
- Installation of HVAC is ongoing
- Architect waiting for Contractor’s partial punchlist on windows and painting
◼︎McLaurin High School
- Ready for Owner’s inspection punchlist
- Cafeteria addition:
- Completing VCT
- Classroom addition CMU is ongoing
◼︎Pelahatchie High School
- Complete remaining punch list items for building J
- Contractor working on the courtyard area
◼︎Puckett High School
- Interior painting on going
- Completing HVAC installation
◼︎Brandon High School
- Polishing concrete floors o Finish grading is ongoing o Installing LAT
- Contractor awaiting additional cast stone
◼︎Stonebridge Elementary
- Laying brick
- Installing ceiling grid
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
- Work is complete in existing building, minus new carpet in library.
- New connector breezeway is complete.
- Work is ongoing at new bus canopy and walkway canopy. New addition is awaiting window installation.
- Interior finishes of the band and choir rooms
◼︎Florence High School
- Interior Selective repairs are approx. 90% complete. Carpet in the library and VCT in select classrooms when the school is on a holiday break.
- New front entry exterior is ready for masonry
- Prepping for new classroom addition slab
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
Building 100 (New Classroom Building)
- Structural steel and floor joist are complete.
- Pedestrian walkway bridge steel has been erected.
- Concrete on second floor metal deck has failed.
- Contractor is currently removing the concrete off the metal deck.
Building 2000 and 2100 (Jr High School)
- Urinal screens pedestals to be replaced during the next school break.
- Water heater has been installed.
- Faculty, staff, and students have full use of the facility.
Building 3000 (Cafeteria)
- Brick installation nearing completion.
- Existing shingle roof has been demolished down to the tectum deck.
- Plywood deck installation will start soon.
Building 4000 (Fine Arts Building)
- Stage framing in completed.
- Stage concrete floor has been placed.
- Mechanical and electrical rough ins continue.
- Exterior brick walls are in progress.
- Steel window restoration in progress
- Sample window to be available after September 21st for review
Building 7100 (Ag Shop)
- Color selection conflict.
- Option to be reviewed.
Site
- Contractor has been maintaining the grass within the construction fence.
- Contractor has cleaned up the
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
|
Pelahatchie Elementary |
Northshore Elementary |
|
Pisgah High School |
Oakdale Elementary |
|
NWR HS Site Package |
Highland Bluff Elementary |
|
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
|
Existing NWR HS Renovations Phase I |
Brandon Elementary |
|
Steen’s Creek Elementary |
Puckett High Dressing Room |
|
Florence Elementary |
Puckett Elementary School |
|
NWR Middle Reroof |
Florence Middle Reroof |
|
NWR Elementary Reroof |
Special Needs Playgrounds |
|
NWR Elementary Additions & Renovations |
Richland Elementary School |
Bond Issue Board Update - August 26, 2020
Project Facilitators – JH&H and Dale|Bailey
◼︎Under Construction
◼︎Complete
◼︎In Design
JH&H PROJECTS
◼︎New Northwest Rankin High School
- Contractor continues to methodically lay CMU, AMU & brick, install curtainwall and storefront, interior metal stud framing & interior finishes (LAT ceilings and gyp board, paint & tile). All trades are in progress.
- Site work continuing to progress. Connection canopy & sidewalks to existing middle school is complete
- Coordination of ongoing work/start of school year with the middle school principal has occurred.
- Project is on schedule.
◼︎Pisgah Elementary
- Renovation work to the existing school is in progress (interior finishes and lighting).
- Coordination of ongoing work/start of school year with the principal has occurred.
- Site work (storm drainage, parking lot replacement) is in progress.
◼︎Flowood Elementary School Additions and Renovations
- Coordination of ongoing work/start of school year with the principal has occurred.
- Asphalt paving and striping is complete.
- Project is on schedule.
◼︎Existing NWRHS Renovations Phase 2
- Interior finish work is progressing (paint, ceiling grid, lighting). All related subcontractor trades are in progress.
- Connection between main building and vine street is in progress. Sidewalk to be completed week of 8/24.
- Coordination of ongoing work/start of school year with the high school principal has occurred and coordination of work continues periodically with school administration.
DALE/BAILEY PROJECTS
◼︎Brandon Middle School
- Building Package
- Laying Block on Bldg N & P
- Hanging bar joist on N & P
- Running conduit in M & L
- Blinds are installed
- Cameras are installed
◼︎McLaurin High School
- Ready for Owner’s inspection punchlist
- Cafeteria addition:
- Awaiting VCT Color
- Classroom addition CMU is ongoing
◼︎Pelahatchie High School
- Complete remaining punch list items for building J
- Contractor working on the courtyard area
◼︎Puckett High School
- Preparing finish grades
- Stage curtains subs on site to field verify
- Glazing in window frames
- Walls primed for painting
◼︎Brandon High School
- Installing gypsum board
- Painting is ongoing
- Installing cast stone
◼︎Stonebridge Elementary
- Exterior masonry to begin the week of 8/24
WIER BOERNER ALLIN PROJECTS
◼︎Florence Middle School Additions and Renovations
- Work is complete in existing building, minus new carpet in library.
- New connector breezeway is 75% complete.
- New sidewalks and entry stairs/ramp have been poured at fine arts addition.
- Work is ongoing at new bus canopy and walkway canopy. New addition is awaiting window installation.
- Work at GED building is 95% complete.
◼︎Florence High School
- Interior Selective repairs are approx. 90% complete. Carpet in the library and VCT in select classrooms when the school is on a holiday break.
- Foundation work, CMU masonry, and roof framing for the new front secure entry and connection corridor is complete.
- CCD 001 was executed and its associated work to remediate the existing soils for the new building foundation is complete.
- Replacement of existing North parking lot, including all soils repair is now complete.
- Foundation work for the new classroom building has begun, and over 50% of concrete grade beams and foundation walls have been poured to-date.
PRYOR AND MORROW PROJECTS
◼︎Richland High Additions & Renovations
- Building 100 (New Classroom Building)
- Structural steel and floor joist are in progress.
- Pedestrian walkway bridge steel has been erected.
- Building 1000 (High School)
- Work has been completed. Final review pending.
- Faculty, staff, and students have full use of the facility
- Building 2000 and 2100 (Jr High School)
- Work had been completed except for paint touch up and minor restroom screens work
- Water heater to be replaced as soon as equipment is delivered.
- Work to be completed during next school break.
- Faculty, staff, and students have full use of the facility.
- Building 3000 (Cafeteria)
- Brick has been delivered to the site and installation will start soon.
- Building 4000 (Fine Arts Building)
- Stage framing in progress.
- Mechanical and electrical rough ins nearing completion.
- Exterior masonry walls are in progress.
- Steel window restoration has commenced.
- Building 5000 (Choir)
- Work has been completed. Final review pending.
- Faculty, staff, and students have full use of the facility
- Building 6000 (Band Hall)
- Work has been completed. Final review pending.
- Faculty, staff, and students have full use of the facility
- Building 7000 (ROTC)
- Work has been completed. Final review pending.
- Faculty, staff, and students have full use of the facility
- Building 7100 (Ag Shop)
- Color selection has been selected. Fabrication soon to be released.
- Site
- Contractor has been maintaining the grass within the construction fence.
- Contractor has cleaned up the site and consolidated all construction material to locations within the laydown area.
- Contractor will be using a section on the new parking lot for parking.
◼︎COMPLETED PROJECTS
McLaurin Elementary |
Richland Upper Elementary |
Pelahatchie Elementary |
Northshore Elementary |
Pisgah High School |
Oakdale Elementary |
NWR HS Site Package |
Highland Bluff Elementary |
Vine Street Building Re Roof |
Flowood Elementary Re Roof |
Existing NWR HS Renovations Phase I |
Brandon Elementary |
Steen’s Creek Elementary |
Puckett High Dressing Room |
Florence Elementary |
Puckett Elementary School |
NWR Middle Reroof |
Florence Middle Reroof |
NWR Elementary Reroof |
Special Needs Playgrounds |
NWR Elementary Additions & Renovations |
Richland Elementary School |